Project at a Glance
Project Ref GTR-2330Colum · Verified 09/2026- Building Type
- Warehouse
- Location
- 2330 Columbia Pike, Arlington, VA 22204
- Roof Area
- 7,306 SF
- Existing System
- Modified bitumen, 30 years old
- Deck Type
- Wood deck
- Installed System
- Fluid-applied high-solids silicone restoration
- Manufacturer
- Progressive Materials
- Field Coating
- PM Pro-Eco Silicone HS 3200 Series
- Coating Color
- White (HS 3201 / LS 2201)
- Dry Film Thickness
- 40 mils minimum DFT
- Seam Treatment
- 20 mil silicone stripe, approx. 2 in. wide, all laps
- Reinforced Repairs
- 3-course silicone and polyester at failed seams and flashings
- Structural Repair
- 50 LF of rotted gutter-line decking and framing rebuilt
- Slope Correction
- Gutter-line slope re-established; PM Pro Slope at low areas
- Surface Preparation
- Power wash at minimum 2,000 PSI
- Bleed-Block Primer
- PM P-160, entire surface at 1 gal/100 SF
- Diagnostics
- Tramex surface scan and CMEX5 pin probe; HIKMICRO M30 post-sunset infrared scan
- Warranty Issued
- 20-year Progressive Materials labor & material
- Start Date
- 07/2026
- Completion Date
- 09/2026
- Duration
- 17 working days
- Building Occupancy
- In operation throughout; no tear-off
- Recordable Incidents
- 0
Executive Summary
What This Project Involved
The roof on this Arlington warehouse was a 7,306-square-foot modified bitumen assembly draining to a gutter along one edge. The membrane across the field had weathered but was still sound enough to serve as a substrate. The problem was concentrated at the gutter line, and it was structural rather than a coating problem: prolonged leakage at the roof edge had kept the wood decking and framing beneath the membrane permanently wet, and the wood had swollen and rotted through.
As that structure deteriorated it lost its shape. The roof edge deflected and curled upward, forming a lip along the gutter line, and the lip acted as a dam. Water running down the roof reached the edge and stopped instead of spilling into the gutter, so it stood in a band along the very edge it was supposed to drain from. The condition was self-worsening: the standing water kept the rotting wood saturated, which let the edge rise further, which held back more water. Additional low areas elsewhere on the roof held water past 48 hours because the original slopes were inadequate.
Fifty linear feet of the gutter line was rebuilt. The membrane was opened, the rotted decking and framing were cut out and replaced with sound material, and the correct edge line and slope were re-established so water reaches the gutter instead of being dammed behind a lip. The rebuilt section was then reroofed and brought into the coating system. The moisture survey performed before restoration identified the remaining wet areas within the assembly, and those were cut out and replaced as well, so nothing saturated was sealed in beneath the new coating. Elsewhere, low areas were built back up with PM Pro Slope and alligatored and heavily cracked areas were filled and smoothed with PM SL 800 Surface Leveler.
With the structure and the drainage corrected, the roof was power washed at a minimum of 2,000 PSI, an adhesion test was performed on the cleaned and dried surface, and PM P-160 Asphalt Bleed-Block Primer was applied over the entire modified bitumen surface at one gallon per 100 square feet. Every membrane lap seam received a 20-mil silicone seam stripe approximately two inches wide, and failed and open seams and flashing failures were rebuilt with three-course silicone and polyester repairs. PM Pro-Eco Sil HS 3200 Series high-solids silicone was then applied in white to a minimum of 40 mils dry film thickness. Progressive Materials inspected the completed roof and issued a 20-year labor and material warranty covering leaks due to silicone material failure.
Starting Point
Existing Conditions
The field membrane was aged but serviceable as a substrate, which is what made this roof a restoration candidate. The failure was concentrated at the gutter line, where a long-running leak had destroyed the wood structure beneath the membrane and, in doing so, reversed the drainage the roof depended on. Conditions were recorded by component so the structural repair could be scoped separately from the coating work.
| Location | Observed condition | Extent | Leak history |
|---|---|---|---|
| Gutter-line structure | Wood decking and framing beneath the membrane swollen and rotted through from prolonged water exposure | 50 LF of roof edge | Severe long-term leakage at the roof edge |
| Roof edge profile | Deteriorated structure had deflected upward, forming a lip that dammed water back onto the roof and blocked it from reaching the gutter | Along the same 50 LF | Standing water held permanently against the edge |
| Drainage | Ponding held past 48 hours in low areas where the existing roof lacked positive slope to the gutter line | 9 ponding areas | — |
| Membrane field | Aged modified bitumen with surface weathering, granule loss, and areas of alligatoring and surface cracking | 7,306 SF | Reported leaks into the warehouse below |
| Membrane lap seams | Weathered laps with open and lifted edges at side and end joints | 3,760 LF of lap seams | Secondary entry points |
| Failed and open seams | Seams separated or split through, requiring reinforced repair rather than coating alone | 325 LF | Active leakage |
| Flashings | Failed base flashing and open terminations at walls, curbs, and penetrations | 12 locations | Reported at multiple locations |
| Alligatored areas | Heavily cracked and alligatored asphalt surface requiring leveling before coating | 800 SF | — |
| Roof insulation | Retained moisture within the assembly, mapped by survey prior to restoration | 300 SF wet, cut out and replaced | Associated with long-term leakage |
| Penetrations | Aged sealant and failed detailing at pipe, vent, and conduit penetrations | 12 penetrations | Reported at multiple penetrations |
How We Know
Investigation & Diagnostics
Two questions had to be answered before this roof could be quoted as a restoration: how far the structural rot at the gutter line actually extended, and whether the rest of the assembly was dry enough to coat. Ponding at a roof edge is a symptom, and the survey was aimed at establishing its cause rather than recording its presence. The moisture survey and the post-cleaning adhesion test are both mandatory steps under the Progressive Materials warranted system.
| Method | Instrument / reference | Finding |
|---|---|---|
| Visual condition survey | Walk-over survey, NRCA inspection practice | Documented weathering of the modified bitumen field, open and lifted laps, failed flashings, alligatored areas, and standing water held along the gutter line rather than draining into it |
| Roof edge and structural probe | Direct probe and examination of the decking and framing at the gutter line | Wood decking and framing found swollen and rotted through across 50 LF; the deterioration had allowed the edge to deflect upward and dam water back onto the roof |
| Moisture survey — surface scan | Tramex surface scan moisture meter, non-destructive, required by the manufacturer before restoration | Swept the full roof area to map retained moisture within the existing assembly so wet material could be cut out and replaced instead of being sealed beneath the new coating |
| Moisture survey — pin probe | Tramex CMEX5 digital moisture meter with 2-pin probe, taken in 8 separate areas of the roof | Provided direct penetrating readings to corroborate the surface scan and confirm the extent of moisture at the areas it flagged |
| Infrared thermographic scan | HIKMICRO M30 Professional thermal imager, post-sunset scan | Located subsurface moisture by thermal signature as the roof released heat after sunset, independently corroborating the areas identified by the moisture meters |
| Core sampling | Full-depth cores cut at flagged areas and patched the same day | Confirmed the existing assembly and verified the extent of the areas identified by the moisture survey and the thermographic scan |
| Adhesion test | Manufacturer-required adhesion test on the cleaned and dried surface | Pass silicone bond to the washed modified bitumen surface confirmed before the field coating was committed |
| Drainage survey | Post-rainfall observation at 48 hours | Confirmed water was being held at the gutter line by the raised edge, and identified 9 further low areas for correction with PM Pro Slope |
| Seam and flashing survey | Lap-by-lap inspection and probe of seam edges and flashing terminations | Separated the laps that required only a standard seam stripe from the failed and open seams and flashing failures that required reinforced three-course repair |
Decision Record
Options Evaluated
Continued repair, silicone restoration, single-ply recover, and full tear-off replacement were evaluated against the documented membrane condition, the extent of the structural damage at the gutter line, the moisture survey results, and the warranty available at the end of each. The decisive point was that the failure was localized and structural rather than a general failure of the membrane: once the 50 feet of rotted gutter-line structure was rebuilt and the slope re-established, the rest of the roof was a sound substrate for a warranted restoration.
| Option | Est. added service life | Tear-off | Disruption to operations | Warranty available | Outcome |
|---|---|---|---|---|---|
| Continued spot repair | 1–3 years | None | Recurring leaks into the warehouse | Workmanship only | Not selected |
| Coating without structural repair | Not viable | n/a | n/a | Not available over rotted structure | Not selected |
| Structural repair plus silicone restoration | 20 years, renewable at term | Localized at the gutter line and wet areas only | Minimal; building stayed in operation | 20-year PM labor & material | Selected |
| Full tear-off replacement | 20–25 years | Full | High; open roof over stored goods | Single-ply manufacturer NDL | Not selected |
Coating the roof without rebuilding the gutter line was rejected outright. A coating applied over rotted decking would have sealed the damage in, left the raised edge damming water exactly as before, and kept the wood wet under a new warranted system — and no manufacturer warranty would stand behind it. Restoration was viable here precisely because the structural defect was identified, isolated, and rebuilt first, at which point the remaining 7,306 SF of membrane was a sound base for a 20-year system without tearing off a roof over an operating warehouse.
What Was Installed
Specified System
The roof was installed to the Progressive Materials Modified Bitumen 20-Year System specification, preceded by the structural reconstruction the gutter line required. The 20-year term is not a function of the coating alone: it requires the prescribed surface preparation and testing, the prescribed repair details at every seam and flashing, a minimum 40 mils dry film thickness in the field, white coating only, and a manufacturer inspection of the completed roof before the warranty is issued. Our full silicone restoration process is described on our roof coatings page.
| Component | Product / installed work | Specification | Purpose / result |
|---|---|---|---|
| Gutter-line reconstruction | Rotted wood decking and framing cut out and replaced with sound material | 50 LF of roof edge rebuilt | Restored a structurally sound roof edge where prolonged leakage had destroyed the wood beneath the membrane |
| Edge slope correction | Correct edge line and slope re-established across the rebuilt section, then reroofed into the existing membrane | 50 LF | Removed the raised lip that had been damming water and restored drainage into the gutter |
| Moisture survey | Non-destructive moisture survey of the full roof area | Required before restoration | Located retained moisture so it could be removed rather than sealed beneath the coating |
| Wet insulation replacement | Saturated areas cut out and replaced | 300 SF replaced to match existing R-value | Removed the trapped moisture that would otherwise have blistered or disbonded the new system |
| Slope correction | PM Pro Slope | Installed at remaining ponding and low areas as required | Re-established positive drainage instead of carrying the ponding forward into the new system |
| Surface leveling | PM SL 800 Surface Leveler | Applied at alligatored and heavily cracked areas as required | Filled and smoothed cracked asphalt so the coating had a sound, continuous surface to bond to |
| Cleaning | Power wash of the full roof area | Minimum 2,000 PSI, rinsed and dried | Removed contamination and weathered surface material so the silicone could bond |
| Adhesion test | Manufacturer-required adhesion test | Performed after cleaning and drying | Confirmed bond to this specific aged modified bitumen surface before full application |
| Bleed-block primer | PM P-160 Asphalt Bleed-Block Primer — single-component, water-based, plasticizer-free acrylic | 1 gallon per 100 SF, spray applied over the entire modified bitumen surface | Formed a barrier between the asphalt surface and the silicone, preventing chemicals bleeding out of the asphalt from yellowing the white coating |
| Seam stripe — all lap seams | Silicone seam stripe over every membrane lap seam | 20 mils, approx. 2 in. wide, approx. 400 LF per gallon, applied before field coating | Built additional thickness over the most vulnerable line on the roof ahead of the field coat |
| Failed and open seams | 3-course repair: silicone, polyester fabric, silicone | Reinforced repair at every failed or open seam | Restored tensile strength and bridging capability where the membrane had already split |
| Flashing failures | 3-course repair: silicone, polyester fabric, silicone | Same reinforced detail at all flashing failures | Rebuilt the wall, curb, and penetration transitions as part of the warranted system |
| Field coating | PM Pro-Eco Sil HS 3200 Series high-solids silicone | 40 mils minimum dry film thickness across the full 7,306 SF | Seamless fluid-applied waterproofing layer over the restored substrate |
| Coating color | White — HS 3201 / LS 2201 | White only for the 20-year system | Required color for the 20-year term; also delivers the reflectivity benefit of a cool roof |
| Final inspection | Progressive Materials manufacturer inspection | Required for the warranted system | Manufacturer verification of the completed roof before the warranty was issued |
| Warranty | Progressive Materials 20-year warranty | 20-year labor and material, covering leaks due to silicone material failure | Manufacturer-backed long-term coverage for the restored roof |
How It Was Delivered
Execution
The structural work came first and the coating last. Because a restoration does not open the field membrane, the only areas exposed at any point were the localized gutter-line reconstruction and the wet areas being replaced, and each was dried in before the end of the shift so the warehouse below stayed protected.
-
Moisture survey and scope development
The roof was surveyed and a non-destructive moisture survey was performed across the full area before any scope was priced, as the Progressive Materials system requires. The survey was run with a Tramex surface scan moisture meter across the roof field, backed up by a Tramex CMEX5 digital moisture meter using a 2-pin probe taken in eight separate areas of the roof. A post-sunset infrared thermographic scan with a HIKMICRO M30 Professional thermal imager was performed as a third, independent check, reading the areas of retained moisture by the heat they held after sunset. Cores were cut at the flagged areas and patched the same day. The gutter line was probed directly to establish how far the rot in the decking and framing actually ran, since that determined whether this roof was a restoration candidate at all.
-
Rebuilding 50 LF of the gutter line
The membrane was opened along the affected roof edge and the swollen, rotted wood decking and framing were cut out and replaced with sound material across 50 linear feet. This was the root cause of the ponding, not a consequence of it: as the wood had rotted it had allowed the edge to deflect upward into a lip that dammed water back onto the roof and held it against the very structure it was destroying. With sound material in place the correct edge line and slope were re-established so water runs into the gutter, and the rebuilt section was reroofed and tied back into the existing membrane.
-
Wet area replacement and slope correction
The saturated areas identified by the moisture survey were cut out and replaced before any coating work began, so nothing wet was sealed in beneath the new system. Remaining low areas that had been holding water past 48 hours were built back up with PM Pro Slope and feathered out into the surrounding field to carry water toward the gutter line, and alligatored and heavily cracked areas were filled and smoothed with PM SL 800 Surface Leveler to give the silicone a sound, continuous surface.
-
Power washing, adhesion testing, and bleed-block primer
The full roof area was power washed at a minimum of 2,000 PSI to remove contamination and weathered surface material, then rinsed and allowed to dry completely. With the surface clean and dry, the manufacturer-required adhesion test was performed to confirm the silicone would bond to this specific aged modified bitumen. PM P-160 Asphalt Bleed-Block Primer was then spray applied over the entire 7,306 square feet at one gallon per 100 square feet. P-160 is a single-component, water-based, plasticizer-free acrylic primer formulated for smooth asphalt roof surfaces; it forms a barrier between the asphalt and the silicone so the chemicals that bleed out of an asphalt roof cannot migrate up and yellow the white coating.
-
Seam striping and three-course repairs
Every membrane lap seam across the roof received a 20-mil silicone seam stripe approximately two inches wide, applied at roughly 400 linear feet per gallon, before any field coating was applied. Laps are where a modified bitumen roof moves and where water gets in first, so they were built up ahead of the field rather than being left at field thickness. Failed and open seams and every flashing failure were rebuilt with a three-course reinforced repair — a base layer of silicone, polyester reinforcing fabric embedded into it while wet, and a second layer of silicone encapsulating the fabric. Curbs, walls, and penetrations were detailed the same way.
-
High-solids silicone applied to 40 mils DFT
PM Pro-Eco Sil HS 3200 Series high-solids silicone was applied in white across the full 7,306 square feet to a minimum of 40 mils dry film thickness, the thickness the 20-year system requires. Coverage was worked section by section with film thickness monitored as the work proceeded, so the specified thickness could be evidenced across the whole roof rather than averaged over it. The finished surface is seamless and highly reflective.
-
Manufacturer inspection and warranty issue
Progressive Materials inspected the completed roof, which is a condition of the warranted system rather than a formality. The thickness record and photographic documentation were submitted with the inspection, and a 20-year labor and material warranty covering leaks due to silicone material failure was issued to the owner.
Measured Outcome
Results
The warehouse has a seamless, white, fully warranted roof that now drains the way it was designed to. The gutter line is sound structure again rather than rotting wood under a membrane, the raised edge that had been damming water is gone, and the existing roof stayed on the building instead of going to landfill. At the end of the 20-year term the system is renewable with a recoat rather than a tear-off.
Verification & Documentation
The project record documents the structural condition found at the gutter line, the pre-restoration testing that established the rest of the roof was a valid restoration candidate, the repair work performed before coating, the coating thickness achieved, and the manufacturer inspection and warranty closeout. Records are retained and available to the owner on request.
- Structural condition record — photographs and probe findings documenting swollen and rotted wood decking and framing across 50 LF of the gutter line, and the upward deflection of the roof edge that was damming water back onto the roof
- Gutter-line reconstruction record — rotted decking and framing cut out and replaced with sound material, correct edge line and slope re-established, and the section reroofed into the existing membrane
- Moisture survey — non-destructive survey completed across the full roof area before restoration, as required by the manufacturer, using a Tramex surface scan moisture meter and a Tramex CMEX5 digital moisture meter with 2-pin probe read in 8 separate areas of the roof, with wet areas mapped for replacement
- Infrared thermographic scan — post-sunset scan with a HIKMICRO M30 Professional thermal imager, independently corroborating the areas of retained moisture identified by the moisture meters
- Core sample record — full-depth cores cut at flagged areas to confirm the existing assembly and the extent of retained moisture, patched the same day
- Wet area replacement — saturated material cut out and replaced before any coating was applied
- Slope correction — PM Pro Slope installed at remaining ponding and low areas and PM SL 800 Surface Leveler applied at alligatored and heavily cracked areas
- Cleaning record — full roof area power washed at a minimum of 2,000 PSI, rinsed, and dried before coating
- Adhesion test — manufacturer-required adhesion test performed on the cleaned and dried surface and passed before the field coating was committed
- Bleed-block primer record — PM P-160 Asphalt Bleed-Block Primer spray applied over the entire modified bitumen surface at 1 gallon per 100 SF, ahead of seam striping and field coating
- Seam stripe record — 20-mil silicone stripe approximately 2 inches wide applied over all membrane lap seams at approximately 400 linear feet per gallon, ahead of the field coat
- Reinforced repair record — 3-course silicone and polyester fabric repairs documented at all failed and open seams and at all flashing failures
- Film thickness record — PM Pro-Eco Sil HS 3200 Series applied in white to a minimum 40 mils dry film thickness, recorded by section during application
- Drainage verification — post-completion observation confirming the rebuilt gutter line carries water into the gutter rather than holding it at the roof edge
- Manufacturer final inspection — Progressive Materials inspection of the completed system, required before the warranted system could be closed out
- Manufacturer warranty — 20-year Progressive Materials labor and material warranty covering leaks due to silicone material failure, issued to the owner
- Photographic record — existing conditions, gutter-line demolition and reconstruction, repairs and seam striping, and completed coating documented by roof area
Installed by GoTech Roofing — OSHA 30-Hour certified supervision with a designated Fall Protection Competent Person on site, and manufacturer-certified applicator status current at the time of installation. This project is the clearest possible illustration of why ponding has to be diagnosed rather than simply coated: the water standing at the roof edge was not a slope design error but the visible symptom of wood rotting away beneath the membrane. A coating applied over it would have looked like a finished roof, sealed the rot in, and left the dam in place.
Photographic Record
Evidence
Original project photographs taken by GoTech Roofing at 2330 Columbia Pike, in sequence: the weathered modified bitumen surface as found, the alligatoring and seam splitting that drove the repair scope, the adhesion, moisture and core testing that had to pass before any coating was committed, the bleed-block primer that keeps asphalt from yellowing a white roof, and the finished silicone system.
Who Did the Work
Project Team & Credentials
Site Supervision
All field crew members assigned to the project had completed OSHA 30-Hour Construction Safety training, with a designated Fall Protection Competent Person on site for the duration of the work.
Manufacturer Certification
GoTech Roofing held current manufacturer-certified applicator status at the time of the work, a condition of the Progressive Materials 20-year warranted system being issued on the completed roof.
Inspection & Reporting
GoTech Roofing commercial roof inspection staff documented the pre-restoration conditions, the structural deterioration at the gutter line, the Tramex moisture survey, the post-sunset HIKMICRO infrared thermographic scan, the core samples, the adhesion test, the repair and seam-striping scope, and the film thickness achieved. Progressive Materials performed the final inspection and warranty closeout.
Common Questions
Silicone Roof Restoration FAQ
These are the questions building owners and facility managers most often ask when an aged modified bitumen roof is leaking, ponding, or showing damage at the roof edge. Each answer explains the general principle so you can evaluate your own building's roof. More detail on our process is on the roof coatings page.
Can a modified bitumen roof be restored with a silicone coating instead of replaced?
Yes, when the assembly below the membrane is dry and structurally sound. Modified bitumen is one of the substrates silicone restoration is best suited to, because the existing membrane stays in place and becomes the base sheet for a new fluid-applied waterproofing layer. What determines eligibility is not the age of the roof but its condition: a moisture survey has to confirm the insulation is dry, any wet areas have to be cut out and replaced, and an adhesion test has to confirm the coating will bond to that specific weathered surface. Structural damage found during that assessment does not rule restoration out, but it does have to be rebuilt first rather than coated over.
Does a roof with two or more existing layers have to be torn off?
Yes, and because the restriction appears in both model codes, the correct citation depends on what kind of building it is. For one- and two-family dwellings and townhouses, the residential provision is 2018 IRC Section R908.3, which governs roof replacement and does not permit a roof recover where the existing roof already has two or more applications of any type of roof covering. For commercial buildings and most multi-family residential construction, the equivalent commercial provision is 2018 IBC Section 1511.3. The effect is the same under either code: where a roof already carries two or more layers, for example modified bitumen installed over an existing built-up roof, a new roof covering cannot legally be installed over the top, and the existing layers have to be removed down to the deck first. That turns a traditional re-roof into a mandatory full tear-off, which is the most expensive and most disruptive part of any roofing project: it is noisy and dirty, it exposes the interior to weather, and in a working building it is the part that interferes most with operations. A silicone restoration is not a new roof covering installation, so the two-layer restriction does not force a tear-off. The existing layers stay on the building and are waterproofed with a fluid-applied coating instead. This project is a warehouse, so the IBC provision is the one that applies.
What happens when the wood decking at a roof edge rots from a long-term leak?
It has to be rebuilt, and the damage is usually worse than it looks from above. Water that gets past the membrane at a roof edge keeps the wood decking and framing beneath it permanently wet, and the wood swells, softens, and eventually loses its structural strength. As it deteriorates it also loses its shape, so the roof edge no longer sits where it was built to sit. That is a structural repair, not a roofing repair: the membrane is opened up, the rotted decking and framing are cut out and replaced with sound material, the correct line and slope are re-established, and only then is the area reroofed and brought into the coating system.
Why would a roof pond with water right next to the gutter?
Because the edge of the roof has risen relative to the field behind it. When the wood structure along a gutter line rots and swells from prolonged leakage, the deck can deflect and curl upward at the edge, forming a lip. That lip acts as a dam: water running down the roof reaches it and stops instead of spilling into the gutter, so it stands in a band along the roof edge. It is a self-worsening condition, because the water that now sits against the edge keeps the rotting wood wet and the lip keeps growing. Coating over it would seal the surface but leave the dam in place, so the structure has to be rebuilt and the slope re-established first.
What is a silicone roof restoration?
A silicone roof restoration is a fluid-applied waterproofing system installed over an existing low-slope roof rather than replacing it. The roof is power washed, repaired, and detailed, every membrane lap seam is reinforced with a silicone seam stripe, failed seams and flashings are rebuilt with reinforced three-course repairs, and a high-solids silicone field coating is then sprayed or rolled over the entire roof to a specified dry film thickness. The result is a seamless, highly reflective membrane that is renewable at the end of its warranty term rather than being torn off and landfilled.
Why does a modified bitumen roof need a bleed-block primer before silicone coating?
To keep the asphalt from discoloring the coating. Chemicals bleed out of an asphalt roof surface and migrate up into the silicone above it, turning a white coating yellow. Progressive Materials P-160 Asphalt Bleed-Block Primer is a single-component, water-based, plasticizer-free acrylic primer designed for smooth asphalt roof surfaces, and it forms a barrier between the asphalt and the silicone that stops that bleed-through. On a Progressive Materials modified bitumen system it is applied over the entire asphalt surface at one gallon per 100 square feet before any silicone goes on. It can be sprayed, brushed, or rolled, and spray application is preferred.
What is a silicone seam stripe and why is it applied before the field coating?
A seam stripe is a heavier band of silicone applied over every membrane lap seam before the field coating goes down. On a Progressive Materials system it is applied at 20 mils and roughly two inches wide, at a coverage rate of about 400 linear feet per gallon. Laps are where a modified bitumen roof moves and where water finds its way in first, so building extra thickness there before the field coat means the most vulnerable line on the roof carries more material than the field, not less. Skipping the stripe leaves the seams at field thickness and is one of the most common reasons a coating fails early.
What is a three-course repair on a roof?
A three-course repair is a reinforced detail built in three passes: a base layer of silicone, a layer of polyester reinforcing fabric embedded into it while wet, and a second layer of silicone over the top that fully encapsulates the fabric. The fabric gives the repair tensile strength and bridging ability that coating alone does not have, which is why it is specified at failed or open seams, at flashing failures, and at penetrations and curbs. Any area that has already moved or split is repaired this way rather than simply being coated over.
How thick does a silicone roof coating have to be for a 20-year warranty?
For a Progressive Materials 20-year system over modified bitumen the field coating must achieve a minimum of 40 mils dry film thickness, and the 20-year color option is white only. Thickness is what drives warranty term on a silicone restoration: shorter warranty terms are written at lower dry film thicknesses and longer terms require more material on the roof. Because the requirement is a dry film thickness, application has to be logged and verified as the work proceeds, and the manufacturer inspects the completed roof before the warranty is issued.
Why is a moisture survey required before a roof restoration?
Because a coating is a vapor-retarding layer, and any water already trapped in the assembly stays trapped underneath it. Wet insulation loses its R-value, rots a wood deck or corrodes a metal one, and will push against the new coating as it tries to escape, which can blister or disbond the system. A non-destructive moisture survey maps where the assembly is wet so those areas can be cut out and replaced before any coating is applied. It is also a manufacturer requirement, not just good practice, on a warranted restoration system.
What is an adhesion test and why is it done before coating a roof?
An adhesion test confirms that the coating will actually bond to the specific roof it is being applied to. A small area is cleaned and dried exactly as the full roof will be, a sample of the coating is applied, and once cured it is checked for bond. Aged roof surfaces vary enormously depending on the original product, how weathered they are, and what has been applied over them previously, so the test is performed on the actual roof after cleaning rather than assumed from the data sheet. It is required after cleaning and drying and before the field coating is committed to.
Can ponding water be corrected without tearing off the roof?
Yes, provided the cause is addressed rather than the symptom. Where the slope is simply inadequate, low areas can be built back up with a pourable or trowel-applied slope compound such as Progressive Materials Pro Slope, installed in the low spots and feathered out into the surrounding field so water is carried to the outlets instead of standing. Heavily alligatored or cracked areas are filled and smoothed with a surface leveler such as PM SL 800 so the silicone has a sound, continuous surface to bond to. Where the ponding is caused by structural deterioration rather than original design, that structure has to be rebuilt first, because no amount of slope compound will fix a roof edge that has physically moved.
Can a warehouse stay in operation during a roof restoration?
In most cases yes, and that is one of the main practical advantages of restoration over replacement. Because there is no tear-off, the existing membrane is never opened, so there is no point at which the interior is exposed to weather, no tear-off debris to move through or around the building, and no need to protect stored goods or racking from an open roof. Localized structural repairs are the exception and are staged and dried in area by area. Access, staging, and any temporary interruption to rooftop equipment are coordinated with operations, and loading dock and yard traffic is kept clear of the work zone.
What does a 20-year Progressive Materials silicone warranty cover?
The 20-year Progressive Materials system carries a 20-year labor and material warranty covering leaks caused by failure of the silicone material, subject to the warranty terms and exclusions. It requires the system to be installed to the published specification, including the minimum 40 mil dry film thickness, white coating, seam striping, and reinforced repairs at failed seams and flashings, and it requires a manufacturer inspection of the completed roof before the warranty is issued. That final inspection is the step that converts a completed coating job into a warranted roof system.
Keep Looking















